Working Schedule Period Manpower Issue 21 APR 21 APR - "1st cargo leave Japan to BNL" 01 MAY 03 MAY 2 "shipped material quick check" 05 MAY 15 MAY 2 "support frame for NaI/target setup" 05 MAY 20 MAY 2 "cabling at area" 05 MAY 20 MAY 2 "cabling at counting house" 13 MAY 15 MAY 1 "chamber gas preparation" 15 MAY 09 MAY 1 "ID/FD chamber startup" 19 MAY 20 MAY 1 "support frame survey" 20 MAY 23 MAY 2 "NaI mount" 20 MAY 23 MAY 1 "DAQ startup for NaI calibration" 23 MAY 23 MAY - "48D48 magnet power on" 28 MAY 09 JUN 2 "NaI calibration" 30 MAY 09 JUN 1 "BD chamber startup" 01 JUN 04 JUN 1 "live target preparation" 09 JUN 09 JUN - "48D48 magnet power off" 09 JUN 09 JUN - "D6 beam line magnets on" 09 JUN 10 JUN 1 "comparator setting" 10 JUN 10 JUN - "48D48 magnet power on" 09 JUN 13 JUN 2 "counter check with beam" 10 JUN 15 JUN 1 "DAQ startup for experiment" 13 JUN 14 JUN 1 "beam line tuning" 14 JUN 16 JUN 2 "beam energy calibration by TOF" 16 JUN 17 JUN 1 "beam line tuning again" 16 JUN 23 JUN 3 "debug and threshold adjust" 23 JUN ? ? 2 "start data taking" 03 JUL ? ? 1.5 "offline analysis for debug"